The major issue with this type of cooled ceiling technique is the possibility of condensation on the piping of the ceiling panels. To avoid an indoor rain storm, the humidity levels of the air must be closely monitored and controlled with a humidifier / dehumidifying system. In order to adhere to the strict guidelines of the Solar Decathlon competition, this monitoring must take place anyway, so this issue really becomes less of a problem. The monitoring of the heating and cooling system will also benefit several other areas of indoor comfort. For example, the ELEMENT will not have any operable windows (firstly because of an increased cost and secondly because of the poor air tightness which would result) therefore, in order to maintain a healthy Indoor Air Quality (IAQ) a Heat Recovery Ventilator (HRV) or a Energy Recovery Ventilator (ERV) will be used to supply fresh air to the house (the principle difference between the two being the HRV only transfers sensible heat while the ERV transfers latent heat as well). The main reasoning behind the decision to avoid operable windows was decreased air tightness that would result from having operable windows.
Mechanical Engineering: Radiant Ceiling Panels Analysis
The major issue with this type of cooled ceiling technique is the possibility of condensation on the piping of the ceiling panels. To avoid an indoor rain storm, the humidity levels of the air must be closely monitored and controlled with a humidifier / dehumidifying system. In order to adhere to the strict guidelines of the Solar Decathlon competition, this monitoring must take place anyway, so this issue really becomes less of a problem. The monitoring of the heating and cooling system will also benefit several other areas of indoor comfort. For example, the ELEMENT will not have any operable windows (firstly because of an increased cost and secondly because of the poor air tightness which would result) therefore, in order to maintain a healthy Indoor Air Quality (IAQ) a Heat Recovery Ventilator (HRV) or a Energy Recovery Ventilator (ERV) will be used to supply fresh air to the house (the principle difference between the two being the HRV only transfers sensible heat while the ERV transfers latent heat as well). The main reasoning behind the decision to avoid operable windows was decreased air tightness that would result from having operable windows.
Construction Progress: Week of May 20
Also, before the rest of the exterior sheathing is installed, gaps in the wall insulation will need to be filled. These gaps have mostly occurred around areas where thicker conduit is running through the exterior wall. For more information on the sprayed-in insulation and the insulation installation, see “Construction Techniques: Spray Foam Insulation.”
Construction Progress: Week of May 13
The North Wall of the Bedroom Module with Permeable Barrier and Window Installed
By June 15 all exterior finishes should be on and interior nearing completion. At this point the mechanical engineering team will be able to install the heating, ventilation and air conditioning system (also referred to as the HVAC system). Once installed, the HVAC system will be tested to insure the optimum indoor air quality (IAQ), an adequate number of air changes per hour (this plays a large part in the providing an optimum IAQ), and one of the most important tests will be to insure the most efficient performance of the vapor compression panels. These tests will make the ELEMENT a pleasant, healthy and energy efficient house in which to live.
Construction Progress: Week of May 6
Construction Progress: Week of Apr 29
Roof Drain Installation Transferring Rain Water from Module to Module
Exterior Sheathing Nearing Completion on the Kitchen Module
Construction Progress: Week of Apr 22
The Bedroom Module showing the Interior Roof Insulation between Roof Joists
ELEMENT Design Development: Solar Panel
http://www.bp.com/subsection.do?categoryId=3050503&contentId=3060168
After the module shift took place, we were able to more adequately maximize the roof area available for solar panels. As seen below, the roof of each module has a solar array consisting of a 12 photovoltaic module units in a 3 x 4 grid. Then attached to the façade of each module there are an additional 4 photovoltaic module for a total of 48 photovoltaic module units to power the house and the electric car.
South Elevation showing the Solar Array
Performance and transportation where the two main drivers behind the design of the solar arrays. The solution to both these issues came when we decided to hinge each group of panels. The 12 units on the roof fold down on top of the roof for ease of transportation while the 4 units on the south façade fold inward against the façade during transport. This hinging will help protect the panels during the trip to
Conceptual Design of Hinged Solar Arrays