Construction Progress: Week of Apr 29

This week the exterior sheathing is being applied. The exterior sheathing will help the modules better protect against shearing forces applied at the roof level during transportation and after the modules have been installed. This sheathing also helps better protect the insulation for the harsh exterior. Also this week, workers will be retro-fitting the insulation so that next week the modules are ready for the electricians to come and run the circuits to power the modules.

Roof Drain Installation Transferring Rain Water from Module to Module

Exterior Sheathing Nearing Completion on the Kitchen Module